Monday 19 October: Complaint form offline

The supplier of our case management system has confirmed that they are experiencing a significant technical issue.

At present, we have no access to the case management system and we are currently unable to provide updates on existing cases.

We are planning on the basis that this could continue for a period of time including for the remainder of this week.

If you would like to check if your complaint is ready for the SPSO or enquire about making a new complaint, please complete our Complaint Checker.  

Please be assured we are doing all we can and will provide updates on our website. 

For an all service update: Service update | SPSO

Investigation Report 200800277

  • Report no:
    200800277
  • Date:
    July 2009
  • Body:
    Scottish Government Housing and Regeneration Directorate
  • Sector:
    Scottish Government and Devolved Administration

Overview
The complainant (Mrs C) raised a number of concerns regarding Communities Scotland (the Grant Provider)'s handling of her application for a Rural Home Ownership Grant (RHOG). Mrs C complained that the Grant Provider and their local agents, failed to follow the correct procedures when processing her application and that communication from the two agencies was poor.

Specific complaints and conclusions
The complaints which have been investigated are that:
(a) the Grant Provider failed to follow their own guidelines when considering Mrs C's RHOG application (upheld); and
(b) communication from the Grant Provider was poor (upheld).

Redress and recommendations
The Ombudsman recommends that the Scottish Government Housing and Regeneration Directorate:
(i) ensure that their agents fully understand their responsibilities with regard to RHOG applications, in particular by ensuring that all applications meet the required criteria and are fully completed prior to submission;
(ii) produce clear guidelines for their agents on presenting a case for consideration of applications with special circumstances;
(iii) require all RHOG applicants to have read and agreed their complete application before signing;
(iv) review Mrs C's case to identify any areas where communication between themselves and the Agent could have been improved; and
(v) formally apologise to Mrs C for the confusion and delay surrounding her RHOG application.

The Scottish Government Housing and Regeneration Directorate have accepted the recommendations and will act upon them accordingly.