Monday 19 October: Complaint form offline

The supplier of our case management system has confirmed that they are experiencing a significant technical issue.

At present, we have no access to the case management system and we are currently unable to provide updates on existing cases.

We are planning on the basis that this could continue for a period of time including for the remainder of this week.

If you would like to check if your complaint is ready for the SPSO or enquire about making a new complaint, please complete our Complaint Checker.  

Please be assured we are doing all we can and will provide updates on our website. 

For an all service update: Service update | SPSO

Investigation Report 200600025

  • Report no:
    200600025
  • Date:
    June 2008
  • Body:
    South Lanarkshire Council
  • Sector:
    Local Government

Overview

The complainant (Mr C) raised a number of concerns regarding the handling of a planning application by South Lanarkshire Council (the Council).

Specific complaints and conclusions

The complaints which have been investigated are that:

  • (a) the letter of 11 July 2005 resulted in unnecessary delay affecting the progression of the application (not upheld);
  • (b) the terms of the letter dated 11 July 2005 which was issued to Mr C's client were inaccurate (upheld);
  • (c) the Council failed to register the application which resulted in an unnecessary two-month delay (not upheld); and
  • (d) the Council failed to issue a letter requesting an extension for dealing with the application as required by statute (not upheld).

Redress and recommendations

The Ombudsman recommends that the Council apologise to Mr C for issuing an inaccurate and misleading letter.

The Council have accepted the recommendations and will act on it accordingly.