Monday 19 October: Complaint form offline

The supplier of our case management system has confirmed that they are experiencing a significant technical issue.

At present, we have no access to the case management system and we are currently unable to provide updates on existing cases.

We are planning on the basis that this could continue for a period of time including for the remainder of this week.

If you would like to check if your complaint is ready for the SPSO or enquire about making a new complaint, please complete our Complaint Checker.  

Please be assured we are doing all we can and will provide updates on our website. 

For an all service update: Service update | SPSO

Investigation Report 200502731

  • Report no:
    200502731
  • Date:
    November 2007
  • Body:
    The Moray Council
  • Sector:
    Local Government

Overview

The complainant (Mr C) was dissatisfied with The Moray Council (the Council)'s handling of his complaints relating to a planning consent for his holiday park and their actions in serving an enforcement notice for breach of a condition of that consent.  He alleged that there was delay (in excess of three months) in responding to his representations and that they failed to reply fully to the seven points of complaint he had raised.

Specific complaints and conclusions

The complaints which have been investigated are that the Council:

  • (a) delayed in responding to his representations (upheld); and
  • (b) failed to reply fully to his representations (upheld).

Redress and recommendations

The Ombudsman recommends that the Council:

  • (i) review their enforcement procedures and produce guidelines which can be audited; and
  • (ii) take steps to meet with Mr C to discuss his outstanding concerns.

The Council have accepted the recommendations and will act on them accordingly.