Tuesday 20 October: Complaint form offline

The supplier of our case management system has confirmed that they are experiencing a significant technical issue.

At present, we have no access to the case management system and we are currently unable to provide updates on existing cases.

We are planning on the basis that this could continue for a period of time including for the remainder of this week.

If you would like to check if your complaint is ready for the SPSO or enquire about making a new complaint, please complete our Complaint Checker.  

Please be assured we are doing all we can and will provide updates on our website. 

For an all service update: Service update | SPSO

Decision Report 201300497

  • Case ref:
    201300497
  • Date:
    January 2014
  • Body:
    Stirling Council
  • Sector:
    Local Government
  • Outcome:
    Some upheld, no recommendations
  • Subject:
    complaints handling

Summary

A local councillor (Mr C) complained on behalf of two of his constituents that works on a neighbouring property had begun without the relevant permit being issued. He was also unhappy with the council's responses to the complaints he made on his constituents' behalf.

Our investigation found that the council officer involved had verbally advised the contractor that the permit would be issued, and was then unexpectedly absent from work when the application was received. We did not uphold the complaint about this, as we decided that in the circumstances it was reasonable for the council to allow the work to progress before the permit was issued. We did uphold the complaint about the council's complaints handling because of the delay in providing Mr C with a response. As the council had taken action as a result of the complaint, by apologising and putting extra resource in place to ensure this did not happen again, we did not make any recommendations.