Tuesday 20 October: Complaint form offline

The supplier of our case management system has confirmed that they are experiencing a significant technical issue.

At present, we have no access to the case management system and we are currently unable to provide updates on existing cases.

We are planning on the basis that this could continue for a period of time including for the remainder of this week.

If you would like to check if your complaint is ready for the SPSO or enquire about making a new complaint, please complete our Complaint Checker.  

Please be assured we are doing all we can and will provide updates on our website. 

For an all service update: Service update | SPSO

Decision Report 201800422

  • Case ref:
    201800422
  • Date:
    December 2018
  • Body:
    River Clyde Homes
  • Sector:
    Housing Associations
  • Outcome:
    Upheld, recommendations
  • Subject:
    repairs and maintenance

Summary

Mr C complained that the association did not respond within a reasonable timescale to his reports of water ingress in his home.

We found that the association's repairs policy states that emergency repairs should be responded to within four hours, urgent repairs within three working days and routine repairs within 20 working days. The association provided no evidence to support how Mr C's reports were categorised, however, it took two months for investigations to be carried out to Mr C's reports of a fault, outwith all timescales. Therefore, we upheld Mr C's complaint.

Recommendations

What we asked the organisation to do in this case:

  • Apologise to Mr C for not responding to his reports of a fault with the roof within a reasonable timescale. The apology should meet the standards set out in the SPSO guidelines on apology available at www.spso.org.uk/leaflets-and-guidance.

What we said should change to put things right in future:

  • Ensure processes are followed to respond to reports of a fault.
  • Ensure repairs are categorised as either emergency, urgent or routine.

We have asked the organisation to provide us with evidence that they have implemented the recommendations we have made on this case by the deadline we set.

Updated: December 19, 2018