Thursday 22 October: Complaint form offline

The supplier of our case management system has confirmed that they are experiencing a significant technical issue.

At present, we have no access to the case management system and we are currently unable to provide updates on existing cases.

We are planning on the basis that this could continue for a period of time including for the remainder of this week.

If you would like to check if your complaint is ready for the SPSO or enquire about making a new complaint, please complete our Complaint Checker.  

Please be assured we are doing all we can and will provide updates on our website. 

For an all service update: Service update | SPSO

Decision Report 201507448

  • Case ref:
    201507448
  • Date:
    November 2016
  • Body:
    Aberdeen City Council
  • Sector:
    Local Government
  • Outcome:
    Some upheld, recommendations
  • Subject:
    policy/administration

Summary

Mr C complained that the council failed to resolve flooding in his house which appeared to be coming from a nearby culverted burn (a burn that is diverted through a pipe). Although the council undertook some investigations including a camera survey which found that the pipe did not follow the expected route, they were not able to survey the full length of the pipe due to an inaccessible manhole. They told Mr C they were not responsible for repairs as the problem appeared to be on private land.

Mr C disagreed and contacted his councillor. After a meeting with all parties the council agreed to undertake a dowser survey (a test used to detect the presence of water) to trace the route of the pipe. The survey was undertaken but the council did not contact Mr C after this or respond to his email asking about next steps.

After investigating these issues we upheld Mr C's complaint about communication. We found it was unreasonable that the council did not share the results of the dowser survey with Mr C or respond to his email about this. We also found the council did not give Mr C clear and consistent information about what he could expect from them as they told him the repairs were not their responsibility but also continued to indicate that future work was anticipated.

We did not uphold Mr C's complaint about the repairs as we found the council had taken reasonable steps to check that the repairs were not their responsibility.

Recommendations

We recommended that the council:

  • apologise to Mr C for the failure in communication;
  • remind relevant staff of the importance of documenting meetings, in particular agreed outcomes; and
  • consider and address relevant staff training needs in relation to clear communication and managing expectations.