Thursday 22 October: Complaint form offline

The supplier of our case management system has confirmed that they are experiencing a significant technical issue.

At present, we have no access to the case management system and we are currently unable to provide updates on existing cases.

We are planning on the basis that this could continue for a period of time including for the remainder of this week.

If you would like to check if your complaint is ready for the SPSO or enquire about making a new complaint, please complete our Complaint Checker.  

Please be assured we are doing all we can and will provide updates on our website. 

For an all service update: Service update | SPSO

Decision Report 201407596

  • Case ref:
    201407596
  • Date:
    October 2015
  • Body:
    Aberdeenshire Council
  • Sector:
    Local Government
  • Outcome:
    Not upheld, no recommendations
  • Subject:
    complaints handling

Summary

Mrs C lives near a former quarry site where planning permission was granted for the erection of buildings and stabilisation works some years ago. When works began she became concerned that the site was operating as a quarry and outside the planning conditions imposed by the council. She complained to the council about this.

The council responded that the developments appeared to be progressing in accordance with the relevant approvals. They said that no conditions had been made in relation to the specific matters that Mrs C raised and that there had been no breaches of the planning conditions, but that concerns about these matters had been passed to relevant departments.

Mrs C was dissatisfied with the council’s responses and complained to us that the council's statement that there had been no breaches of planning conditions was inaccurate. Mrs C's specific concern was that the site was operating outside the times set out in the conditions relating to the two approvals.

After investigating Mrs C's complaint, we found that the operating times stated in the conditions related to after the development had been completed, not during its construction and, therefore, we did not uphold the complaint.

Updated: March 13, 2018