Thursday 22 October: Complaint form offline

The supplier of our case management system has confirmed that they are experiencing a significant technical issue.

At present, we have no access to the case management system and we are currently unable to provide updates on existing cases.

We are planning on the basis that this could continue for a period of time including for the remainder of this week.

If you would like to check if your complaint is ready for the SPSO or enquire about making a new complaint, please complete our Complaint Checker.  

Please be assured we are doing all we can and will provide updates on our website. 

For an all service update: Service update | SPSO

Decision Report 201402826

  • Case ref:
    201402826
  • Date:
    October 2015
  • Body:
    Comhairle nan Eilean Siar
  • Sector:
    Local Government
  • Outcome:
    Some upheld, recommendations
  • Subject:
    handling of application (complaints by opponents)

Summary

Ms C built a new house. A planning application was submitted for another new house to be built on the neighbouring plot of land. Ms C was not notified of the proposed development and, therefore, missed the opportunity to submit representations. The development was subsequently approved. When she learned of the approval, Ms C wrote to the council outlining her objections which included the close proximity, overlooking and overshadowing of the new house to her home. She also objected to the council’s approval of a late decision to relocate the new house within the site without consulting owners of neighbouring properties.

The council accepted that they had not issued a neighbour notification notice to Ms C before giving consent for the new development. This was because her new house did not yet show on the maps that were used to identify neighbouring properties. However, the council felt that they had met their obligation to advertise details of the development in the local press.

We found that advertising in the local press was insufficient and there was a clear requirement for the council to notify Ms C. We were critical of their failure to do so and sought evidence of the procedural changes they have implemented to avoid similar problems in the future. That said, we were satisfied that the points she raised as objections had been considered by the planning officer before the planning permission was granted. We were also satisfied that the relocation of the property was permissible as a non-material variation to the original plans and that no neighbour notification was required for this.

Recommendations

We recommended that the council:

  • issue a written apology to Ms C for failing to properly notify her of the planning application; and
  • demonstrate to us that changes to the neighbour notification process have now been implemented to ensure that all neighbours (including recent/new builds) will be notified.