Tuesday 20 October: Complaint form offline

The supplier of our case management system has confirmed that they are experiencing a significant technical issue.

At present, we have no access to the case management system and we are currently unable to provide updates on existing cases.

We are planning on the basis that this could continue for a period of time including for the remainder of this week.

If you would like to check if your complaint is ready for the SPSO or enquire about making a new complaint, please complete our Complaint Checker.  

Please be assured we are doing all we can and will provide updates on our website. 

For an all service update: Service update | SPSO

Decision Report 201205182

  • Case ref:
    201205182
  • Date:
    December 2013
  • Body:
    The Highland Council
  • Sector:
    Local Government
  • Outcome:
    Not upheld, no recommendations
  • Subject:
    handling of application (complaints by opponents)

Summary

The owners of the yard next to Mr C's house submitted a planning application for the replacement and relocation of their boiler house and drying kilns. Mr C complained that, although the application was approved with conditions attached to the permission, the council failed to enforce those conditions. He said that as a consequence he had suffered horrendous noise levels. Mr C alleged that the council failed to assess the impact of the planning consent on his home, failed to follow the correct procedures and pursue enforcement action, and failed to assess his subsequent complaint properly.

The complaint was investigated and we obtained independent advice from one of our planning advisers. We made further enquiries of the council, and gave all the relevant information (including planning documentation and all the complaints correspondence) careful consideration. The planning adviser said that the council acted reasonably and early by ensuring that a noise impact assessment report was obtained for the proposed development and was reflected in the conditions attached to the planning permission. When some of the conditions were not met, the council considered taking enforcement action but decided that it would be more appropriate to have their environmental health department lead on the matter of noise nuisance. The planning adviser confirmed that this was a reasonable decision, as enforcement action is discretionary and the environmental health department could use statutory measures to address matters that might otherwise be outside the scope of the planning authority. He noted that the council had retained the option of taking enforcement action should they wish to pursue it in the future.

Mr C undoubtedly suffered noise nuisance and we found that the council acted on his complaints about this, although not in the way he would have wished. We did not uphold his complaint, as it could not be said that they did not understand his complaint or failed properly to assess it.