Tuesday 20 October: Complaint form offline

The supplier of our case management system has confirmed that they are experiencing a significant technical issue.

At present, we have no access to the case management system and we are currently unable to provide updates on existing cases.

We are planning on the basis that this could continue for a period of time including for the remainder of this week.

If you would like to check if your complaint is ready for the SPSO or enquire about making a new complaint, please complete our Complaint Checker.  

Please be assured we are doing all we can and will provide updates on our website. 

For an all service update: Service update | SPSO

Decision report 201203650

  • Case ref:
    201203650
  • Date:
    April 2013
  • Body:
    Dumfries and Galloway Council
  • Sector:
    Local Government
  • Outcome:
    Not upheld, no recommendations
  • Subject:
    policy/administration

Summary

Mr and Mrs C said that in June 2012 a building control officer inspected on-going works to their home extension and verbally told them that the walls complied with building regulations. As a result of this they continued construction. At a further inspection in August, however, some of the works that Mr and Mrs C believed had already been inspected were found not to comply with the approved plans and building regulations. Mr and Mrs C complained about this, saying that, had they known about the problem after the earlier visit, they would have stopped construction until it was resolved.

Our investigation found that the June inspection was solely for the purpose of reviewing the build to the open drain and sub-structure of the extension and did not involve the walls. We also noted that the building control officer wrote to Mr and Mrs C's agent immediately after the August inspection to notify them that aspects of the build did not comply with approved plans and building regulations.

It is the developer's responsibility to construct their development in accordance with the approved plans. The inspection process is not designed to control work on site but simply to examine whether a particular stage of the build being inspected is constructed in accordance with building regulations. As responsibility for ensuring that the build was in accordance with the approved plans fell to Mr and Mrs C, and as the June inspection was solely for the purpose of examining the open drain and sub structure, we did not uphold the complaint.

Updated: March 13, 2018